Most research credit cases are lost on records, not on science. The law requires records detailed enough to prove that each claimed dollar was spent on qualified research in a specific business component, and the Tax Court has repeatedly denied credits where the activity may well have qualified but the records did not show it. This page explains the legal standard, the cost-to-activity link examiners look for, what contemporaneous evidence carries weight, and how the 2026 Section G rules change what must be on the return.

Last verifiedNovember 9, 2026Rules effectiveAll open years; Section G business component reporting required for tax years beginning after Dec. 31, 2025

At a glance

Legal standard
Records in sufficiently usable form and detail to substantiate that expenditures claimed are eligible for the credit [1]
General duty
Every person liable for tax must keep the records the Secretary prescribes [2]
Nexus
Costs must be tied to specific business components and qualified activities; arbitrary or unsupported allocations should not be accepted [4]
Business component level
The four-part test is applied separately to each business component, so evidence must be organized the same way [3]
On the return
Section G requires per-component QREs for tax years beginning after 2025, subject to exceptions [6]
Court practice
Credits limited to QREs proven with contemporaneous records [8][7]

The rule, explained

The regulation's standard is plain: keep records in sufficiently usable form and detail to substantiate that the expenditures claimed are eligible. The research credit does not require a special form of documentation, and there is no rule that records must be created at the time of the research. But contemporaneous records are far more persuasive, and the burden of proof is on the taxpayer.

What examiners look for is the link between dollars and qualified activity, which the IRS calls nexus. A claim must show which business component the research related to, what uncertainty existed, how the team evaluated alternatives, who did the work and how much of their time it took, and which supplies and contractors were involved. A wage percentage from a manager's recollection, applied to a whole department, is the classic example the IRS's audit guide says should not be accepted.

The Tax Court has held that line repeatedly. In Siemer Milling, the credit failed because the record showed no process of experimentation. In George, the court allowed credits only for QREs the poultry producer could substantiate with contemporaneous records and cut the simplified credit to 6% because prior-year QREs were not proven. In Little Sandy Coal, the taxpayer could not show that 80% of its activities on each vessel were experimentation. In Phoenix Design Group, the projects lacked identification of the information sought.

From 2026, Section G of Form 6765 asks for QREs by business component on the return, with wages split between direct research, supervision and support, and the information sought listed for amended claims. Documentation that is organized by component during the year now feeds the return directly. Records organized only by cost center will need to be rebuilt each year.

Statutory and regulatory detail

Treas. Reg. §1.41-4(d) requires a taxpayer claiming the research credit to retain records in sufficiently usable form and detail to substantiate that the expenditures claimed are eligible for the credit, and states that the general record retention rules of §1.6001-1 apply [1]. IRC §6001 requires every person liable for any tax to keep such records as the Secretary prescribes [2]. IRC §41(d)(2)(A) applies the qualified research tests separately to each business component [3].

The Research Credit Claims Audit Techniques Guide describes the nexus problem as the inability to connect specific research projects and activities to the qualified expenses, notes that project-based accounting generally establishes nexus while cost center accounting may not, states that arbitrary and unsupported allocations should not be accepted, and says that disallowance of part or all of a cost center may be appropriate where the substantiation rests only on estimates [4]. The general research credit audit techniques guide addresses examination of each element of the credit [5].

In Siemer Milling Co. v. Commissioner, T.C. Memo. 2019-37, the credit was denied because the record did not show a process of experimentation [7]. In George v. Commissioner, T.C. Memo. 2026-10, credits were allowed only for QREs substantiated with contemporaneous records [8]. In Little Sandy Coal Co. v. Commissioner, the Seventh Circuit affirmed the denial where the taxpayer offered no principled way to show that at least 80 percent of its activities were experimentation [9]. In Phoenix Design Group v. Commissioner, T.C. Memo. 2024-113, the projects lacked identification of the missing information [10]. The Instructions for Form 6765 require Section G for tax years beginning after 2025 subject to stated exceptions, with column 49(f) required for amended-return claims [6].

Tax-year applicability

Which years each rule applies to, and the law that set it.

Tax yearsRuleAuthority
All open yearsRecords sufficient to substantiate eligibility; records kept under §6001.Treas. Reg. §1.41-4(d); IRC §6001 [1] [2]
Tax years beginning before Jan. 1, 2026Section G optional on original returns.Instructions for Form 6765 [6]
Tax years beginning after Dec. 31, 2025Section G required by business component unless an exception applies.Instructions for Form 6765 [6]

Worked example

Fenwick Cold Chain · Insulated pharmaceutical shipping containers, Wisconsin · illustrative figures, not a real taxpayer.

Fenwick developed a phase-change shipper that holds 2–8°C for 120 hours. The example compares two ways it could support $1.4 million of 2025 wage QREs for the project. Figures are illustrative.

Fenwick Cold Chain: R&D tax credit documentation requirements: what the IRS expects

  • Approach A: in March 2026, the engineering director estimates that 70% of eight engineers' time went to the shipper; no other records
  • Approach B: weekly time entries coded to the shipper project; a design log of 23 test configurations with thermal chamber data; a decision memo recording why two insulation materials were rejected
  • Eight engineers' total W-2 wages: $2,000,000
StepItemAmount
AEstimate applied to department wages$1,400,000 claimed
A at examUnsupported allocation; no evidence of experimentationHigh risk of full disallowance
BTime entries total $1,360,000 of wages on the project$1,360,000 claimed
B at examTime, tests and decisions tied to one business componentSupported

Common preparer mistakes

  • Relying on year-end interviews and percentage estimates instead of time records.
  • Keeping technical records by product line but cost records by department, with no bridge between them.
  • Writing project narratives years later that describe generic engineering instead of specific uncertainties and tests.
  • Not keeping evidence of failed alternatives, which is often the best proof of experimentation.
  • Assuming a consultant's study binder is substantiation when it does not point to underlying records.

IDR and audit red flags

The document requests and questions examiners actually send on this topic, with what weak and strong support look like.

  1. IDR request: For each business component, provide the documents created during the research that show the technical uncertainty, the alternatives considered, the tests performed and the results.

    Weak support
    A narrative prepared for the claim, with no underlying documents.
    Strong support
    Design reviews, lab notebooks, test reports, tickets and decision memos dated during the work.
  2. IDR request: Explain how wages, supplies and contract research were tied to each business component, and provide the records used for the allocation.

    Weak support
    Department percentages based on manager estimates.
    Strong support
    Project time records, purchase orders coded to projects, and statements of work tied to components.
  3. IDR request: Identify the individuals interviewed in preparing the claim, their roles during the claim year, and any documents they relied on.

    Weak support
    Interviews of current managers who were not present during the year.
    Strong support
    Interview notes corroborated by contemporaneous documents for each statement relied on.

Bate Levina Meylan and Chua's IDR guides: What an IRS IDR is · How to respond to R&D IDRs · Common R&D IDR requests

Where it shows up on Form 6765

Each section below links to its line-by-line walkthrough.

SectionLinesWhat this topic affects
Section G49–56Business component information and per-component QREs.
Section E37–40Number of components, officers' wages, acquisitions and new categories of expense.

FAQs

Do records have to be created at the time of the research?

The regulation does not say so; it requires records in sufficiently usable form and detail to substantiate eligibility. In practice, records created during the work carry much more weight, and the Tax Court in George allowed credits only for QREs supported by contemporaneous records. Reconstructions are possible but must be tied to evidence that existed at the time.

Are time-tracking systems required?

No statute or regulation requires a time-tracking system. But wages must be allocated to qualified services, and Treas. Reg. §1.41-2(d) uses time actually spent as the default allocation method. Without time records, the taxpayer must prove the allocation another way, and the IRS audit guide treats unsupported percentages as insufficient.

What counts as good evidence of experimentation?

Records that show alternatives being evaluated: design iterations, simulation runs, prototype test results, failed approaches, and decisions about which path to take and why. A single final design with no record of what was tried, as in Siemer, is weak evidence. Engineers' existing working documents are usually the best source.

How long should research records be kept?

At least as long as the return can be examined or amended. For the research credit, that often extends well beyond three years, because unused credits carry forward and base-period QREs are needed for later years' computations. Many companies keep research records for the life of the carryforward plus the limitations period.

Does Section G change documentation requirements?

It changes what must be on the return. For tax years beginning after 2025, most filers must report QREs by business component, with wages split into direct research, supervision and support. Records that are already organized by component make Section G a summary; records organized only by department have to be rebuilt every year.

Official sources

Primary authority only. Court opinions are cited only where we read the opinion.

Statutes

  1. [2] Statute

    26 U.S.C. §6001, Notice or regulations requiring records, statements, and special returns

    U.S. Code (Cornell Legal Information Institute)

    Accessed November 9, 2026

  2. [3] Statute

    26 U.S.C. §41, Credit for increasing research activities

    U.S. Code (Cornell Legal Information Institute)

    Accessed November 9, 2026

Treasury regulation

  1. [1] Treasury regulation

    Treas. Reg. §1.41-4, Qualified research for expenditures paid or incurred in taxable years ending on or after December 31, 2003

    Electronic Code of Federal Regulations (eCFR)

    Accessed November 9, 2026

IRS form or instructions

  1. [6] IRS form or instructions

    Instructions for Form 6765, Credit for Increasing Research Activities (Rev. December 2025)

    Internal Revenue Service

    Accessed November 9, 2026

IRS guidance

  1. [4] IRS guidance

    Research Credit Claims Audit Techniques Guide (RCCATG): Credit for Increasing Research Activities §41

    Internal Revenue Service, Large and Mid-Size Business Division

    Accessed November 9, 2026

  2. [5] IRS guidance

    Audit Techniques Guide: Credit for Increasing Research Activities (IRC §41)

    Internal Revenue Service, Large Business and International

    Accessed November 9, 2026

Court opinions

  1. [7] Court opinion

    Siemer Milling Co. v. Commissioner, T.C. Memo. 2019-37

    United States Tax Court (opinion obtained from the court's DAWSON system)

    Siemer Milling Co. v. Commissioner, T.C. Memo. 2019-37 (U.S. Tax Court, Apr. 15, 2019), Docket No. 21655-15

    Held: Credits were denied because the flour miller offered no evidence that it formulated or tested hypotheses, modeled, simulated or evaluated alternatives, so it showed neither a process of experimentation nor that substantially all of its activities were part of one.

    Docket: dawson.ustaxcourt.gov/case-detail/21655-15

    Accessed November 9, 2026

  2. [8] Court opinion

    George v. Commissioner, T.C. Memo. 2026-10

    United States Tax Court (opinion obtained from the court's DAWSON system)

    George v. Commissioner, T.C. Memo. 2026-10 (U.S. Tax Court, Feb. 3, 2026), Docket Nos. 27494-16, 21889-21

    Held: A poultry producer's flock-health and vaccine trials supported credits only for QREs it could substantiate with contemporaneous records; because it proved no QREs for the three prior years, its simplified credit was limited to 6% of QREs.

    Docket: dawson.ustaxcourt.gov/case-detail/27494-16

    Accessed November 9, 2026

  3. [9] Court opinion

    Little Sandy Coal Co. v. Commissioner, No. 21-3145 (7th Cir. 2023)

    United States Court of Appeals for the Seventh Circuit (via govinfo.gov)

    Little Sandy Coal Co. v. Commissioner, No. 21-3145 (7th Cir. Mar. 7, 2023), affirming T.C. Memo. 2021-15

    Held: The credit was denied because the shipbuilder offered no principled way to show that at least 80 percent of its activities for each vessel were elements of a process of experimentation; generalized uncertainty, novelty and arbitrary time estimates were not enough.

    Accessed November 9, 2026

  4. [10] Court opinion

    Phoenix Design Group, Inc. v. Commissioner, T.C. Memo. 2024-113

    United States Tax Court (opinion obtained from the court's DAWSON system)

    Phoenix Design Group, Inc. v. Commissioner, T.C. Memo. 2024-113 (U.S. Tax Court, Dec. 23, 2024), Docket No. 4759-22

    Held: None of three mechanical, electrical and plumbing engineering projects involved qualified research, as a whole or under the shrinking-back rule, because the firm never identified the specific information unavailable to its engineers at the outset or explained how they reached their solutions.

    Docket: dawson.ustaxcourt.gov/case-detail/4759-22

    Accessed November 9, 2026

Research methodology

Researched by
Bate Levina Meylan and Chua Research
Last verified
November 9, 2026
Primary sources checked
10

Every rule on this page was read in the Internal Revenue Code, Treasury regulations, the current Form 6765 instructions, Chief Counsel Memorandum 20214101F, LB&I memoranda LB&I-04-1222-0026 and LB&I-04-0125-0001, IRS news release IR-2025-99, the IRS refund claim FAQs and the IRS research credit audit techniques guides. Tax Court opinions were read in full from the court's DAWSON system. Anything we could not confirm is tagged for verification.

How we research · Report a correction

Bate Levina Meylan and Chua audit defense

Records that hold up are built during the year.

Bate Levina Meylan and Chua helps set up project codes, test logs and decision records that match your Section G components, so if the claim is examined the records already exist.